Go

Australia - A Logistical Nightmare but Well Worth the Effort

Ranger Uranium mine in Northern Territory recently installed a new 12 metre diameter leech feed thickener (tank). The thickener was designed as part of the laterite project on site.

01 February 2008

Normally a thickener would be built, lined and commissioned on site, however FLSmidth Minerals (formally Dorr-Oliver Eimco) had another idea: why not build the 12 metre steel thickener in Darwin and deliver it on site in one piece? FLSmidth Minerals’ chief engineer, Simon Tuner, engineering manager, David Broadhurst, and project manager, Adam Jennians, were up to the challenge.

The thickener was constructed by EC&E Pty Ltd at Berrimah, near Port Darwin.

A natural rubber lining was installed whilst in the factory by Linatex. “Being able to work in a controlled environment – out of the sun, the dust and in a constant temperature – meant that the quality of the rubber lining would be assured,” said Adam Jennians. “Also the coast of construction in a factory was much cheaper than construction on site.”

Delivery to the mine has a Herculean feat in itself and involved a crane, a semi trailer and a 230Km drive down the Arnhem Highway with a 12 metre wide load.

“The physical effort was one thing, but the maze of red tape and overlapping government jurisdictions and approvals was a logistical nightmare,” said Adam. “We had to knock-down and rebuild traffic lights and road signs along the way, but  getting a collection of government departments to agree with each other was the big challenge but determination and perseverance prevailed.”

After an eight hour drive the thickener was delivered and installed on-site in less than four hours. The rubber lined mechanicals, bridge and drive were bolted in place ready for connection to the processing plant.

The thickener was fully operational within two weeks.

“The main advantage of building the tank off-site was the lack of disruption to the mine’s normal operation,” adds Adam. “Just another impossible task delivered on time and budget by FLSmidth Minerals. We can laugh about it now, but it really was a difficult job accomplished by a great team effort. And, most importantly, the client’s happy.”

Contact FLSmidth Minerals

Global Contacts

Global Contacts

Select the country above you wish to contact.
24 Hour Emergency Contacts

24 Hour Emergency Contacts

Select the country above you wish to contact.